| Week 1 (July 8) | 
      Trees cut, outside shingles stripped,
framing begins. | 
    
| Week 2 (July 15) | 
      Rough framing | 
    
| Week 3 (July 22) | 
      Kitchen demolition, rough electrical,
rough framing continues | 
    
| Week 4 (July 29) | 
      Rough plumbing, electrical and plumbing
inspections, plaster prep, boiler replaced (delayed by heating company; happening Aug. 12) | 
    
| Week 5 (Aug. 5) | 
      Board and plaster (didn't happen this week, should happen week 6; electrical, plumbing continued this week) | 
    
| Week 6 (Aug. 12) | 
      Pergo flooring installed in eating area,
kitchen cabinets installed (also boiler replaced - happened Mon, board and plaster scheduled. Pergo hasn't happened yet) | 
    
| Week 7 (Aug. 19) | 
      Cabinet installation cont., trim work,
countertop prep work (Board and plaster work for walls finished this week, cabinets likely next week) | 
    
| Week 8 (Aug. 26) | 
      Trim, countertop work (Cabinets delivered and installed; appliances moved into place; counter template done) | 
    
| Week 9 (Sept. 2) | 
      Tile floor and backsplash installed in
kitchen work area, plumbing and electrical finished, appliances hooked up (Actual: Pergo installed. Counter installation likely week 10, tile floor week 11, backsplash week 12) | 
    
| Week 10 (Sept. 9) | 
      Tile backsplash grouting finished, final
inspection, fabulous new kitchen ready for use. (Actual: Counters, sink, faucet installed)  | 
    
| Week 11 (Sept. 16) | 
      Actual: Lots of carpentry work, and work starts putting down our tile floor.  | 
    
| Week 12 (Sept. 23) | 
      Installation of tile floor continues, plastic dust shields removed, appliance electrical hookups and backsplash installation.  | 
    
| Week 13 (Sept. 30) | 
      Pergo floor uncovered, dryer installed.  |